Rough-in is the electrical work done while the frame is open: cables run through the walls and ceiling, and boxes go where every power point, switch and light will sit. Fit-off comes after the plasterboard, painting and cabinets: the electrician fits the actual power points, switches, lights and appliances, connects the switchboard, then tests everything. Rough-in sets the layout. Fit-off makes it work.
What happens at electrical rough-in?
Rough-in happens after the frame and roof are up and before the walls are lined. The electrician:
- Runs cable from the switchboard position to every point in the plan.
- Fixes brackets and boxes for power points and switches.
- Leaves cable at each light, fan, oven, cooktop and air conditioner position.
- Runs any conduit for data, TV or future work.
Once the plasterboard goes on, moving a point means cutting walls. So rough-in is the last easy chance to change the layout.
What happens at fit-off?
Fit-off comes near the end of the build, after painting and once the kitchen and bathrooms are in. The electrician fits the power points, switches, downlights, fans and outdoor lights, connects the oven and cooktop, terminates the switchboard, then tests every circuit before the power is handed over.
What should I decide before rough-in?
Anything that needs a cable in the wall. That means power point positions and how many, switch positions, every light and fan, outdoor lights and points, and whether you want an EV charger now or a cable ready for later. Our post on electrical planning for a new build goes through the list.
Can changes be made between rough-in and fit-off?
Small ones, sometimes. A fitting can change style if it uses the same cable. Moving a point or adding one after the walls are lined means cutting and patching, and that costs time on the builder’s program. Walk the frame with the electrician before lining if you can.
Who does rough-in and fit-off for new homes around Moreton Bay?
Fins Up Electrical wires new homes from rough-in to fit-off, working to the builder’s program. Andrew has 16 years on the tools, licence 91921, and you deal with him direct. Quotes are free and fixed before we start. See our new home electrical page.
Want this sorted? New home electrical from Fins Up.
Licensed electrician, licence 91921. Free quote before any work starts. Open 24 hours Monday to Saturday.
Common questions
How long between rough-in and fit-off?
That depends on the builder’s program. Fit-off waits for plastering, painting, cabinets and tiling to finish.
Is the switchboard done at rough-in or fit-off?
The board position and incoming cables are set early. The board is terminated and tested at fit-off.
Can I add power points after rough-in?
Yes, but once walls are lined it means cutting in. It is quicker and neater to decide before lining.